Baldivis

Barri Barri Reserve – Baldivis off leash dog exercise area
Access will be restricted to the construction area from Saturday 19 May 2018 to Saturday 2 June 2018.

Elm Reserve – Drainage upgrade
One (1) existing drainage bubble-up pit will be replaced within Elm Reserve. Works are scheduled to commence on Monday 28 May 2018 and are expected to be completed by Friday 1 June 2018. Residents are advised to avoid this reserve while the works are underway.

Gunnedah Reserve – Drainage upgrade
Works are continuing to replace three (3) existing drainage bubble-up pits within Gunnedah Reserve and are expected to be completed by Friday 25 May 2018. Residents are advised to avoid this reserve while the works are underway.

Zedora Park – Replacement of play equipment
Works are scheduled from Saturday 19 May 2018 to Saturday 2 June 2018. The playground will be closed during this time.

Mundijong Road / St Albans Road – Road Widening for a new right turn lane (eastbound)
The eastbound lane of Mundijong Road will be closed during working hours (approx. 7:00am to 3:00pm) with a “stop/go” arrangement in place to allow Mundijong Road traffic (both directions) to travel through the site. There will be some delays to through traffic. The eastbound lane of Mundijong Road will be open outside of these working hours; however, the site will be under traffic management with a reduced speed. Anticipated completion date is late August 2018.

Nairn Drive – Blaxland Terrace to Cottonwood Drive Second carriageway construction
Works have recommenced with the new second carriageway under construction. Bramall Terrace (between Nairn Drive and Smirk Road) will be closed to through traffic to allow reconstruction works at the Nairn Drive / Bramall Terrace intersection, however local residents in the closed section of Bramall Terrace will retain access to their properties. Detour route is in place for traffic turning into Bramall Terrace from Nairn Drive. Anticipated completion date is late September 2018

Rockingham

Lynx Reserve – Replacement of play equipment
Works are scheduled from Saturday 19 May 2018 to Saturday 2 June 2018. The playground will have restricted access during this time

Safety Bay

Centenary Park – Shelter replacement
Works are scheduled to commence on Monday 21 May 2018 and should be completed before end of May 2018

Secret Harbour

Secret Harbour Foreshore – All Abilities Playground
Works have commenced and the site is fenced off. Public access is available between the carparks at Palisades Boulevard and Palermo Cove, on the eastern side of the site following the footpath. The carparks remain open. Official opening on Friday 6 July 2018.

Shoalwater

Baybreeze Promenade / Oceanrunner Boulevard Reserve – New play equipment
Access will be restricted to the construction area from Saturday 19 May 2018 to Saturday 2 June 2018.

McLarty Hall – Asbestos removal
Works are scheduled to commence on Monday 21 May 2018 and should be completed by Tuesday 29 May 2018. Safety Bay Bowling Club Toilet refurbishment Works have commenced and are scheduled for completion in June 2018.

Warnbro

Warnbro Recreational Oval – Replacement of play equipment
Works are scheduled to commence Saturday 19 May 2018 to Saturday 2 June 2018. The playground will have restricted access during this time.

 